A building at upper hill next to the Moi university administration block
It is a
building that was stated in the year 1998 by world bank following a requisition
by Moi university management of the need of a well-established science complex
lab to enable students pursuing science courses have enough practical’s before getting into the field, the construction was to be completed within
two years according to Philip Chirchir the university designing
officer but then money was
fraudulently misused by senior directors of the university. Professor Barasa in his letter yesterday advised the
management to put measures in place to wind up the building to ease congestion
of students in a small laboratory at the school of biological science which
serves students from the faculty of social science, biological science, engineering
and education science. If this is done then Moi University will have their
students doing more of practical’s unlike theories which they are used to.
Some golden should speak to our missions and visions even as we progress in life...it you should start something then should you finish it...the building was started probably with some psyche and now its old before its utilized not completed
ReplyDeleteimagine! soon it will even collapse.
Deleteand that is why some people suffer there at campus outside campus
ReplyDeletehahahaha eti campus outside campus.it sounds odd'
Deletetrue fact and that is just one of many stalled projects in the institution. no accountabillity!!!
ReplyDeleteaudit reports are surely not even authenticated in the institution. Many fails in every field
ReplyDeletewhere are the auditors? we should see people being sued for that matter kellowz
Deleteit is said don't start what you cannot finish. proper planning should be implemented in any project
ReplyDeletebut world bank gave out money to ensure completion of the whole building, i wonder why Kenyans are greed and particularly in moi.
Delete